Sunday, April 15, 2012

4/15/2012 EMS Kitchen, 2nd Floor Carpet and the Fence is Down

 West Side

 South Side

East Side


 Carpet in the VHC President's Office.

 Sidewalks in on the east side.

 Carpet in the EMS Bunk Rooms.

 Cabinets in the EMS Kitchen.

 Shower in the EMS Decon Room.

 More work to do in the IT Room.

 3-Bay sink in the VHC Gear Wash Room for SCBA maintenance.

 Mop sink in the VHC Gear Wash Room.

 Organizer in the VHC Watch Room.

 Sport floor installed in the Fitness Room.

 Under Ambo Storage Room.

 Curbs and sidewalk in the east parking area.

 Sidewalks and topsoil on the east side.

Flag poles in the east parking lot.

Sorry for the picture quality his week. I'm on the disabled list and had to send Sam through with the point and shoot.

Sunday, April 8, 2012

4/8/2012 Exterior Lighting, EMS Gear Grid and VHC Ramp

 West Side

 South Side

East Side

 IT Room. Wow!

EMS Trip Sheet Room 

 EMS Junior Member Area

 EMS Bays with line striping and Kitchen cabinets to be installed.

 EMS gear grid

 EMS Pantry

 EMS Large Bunk Room.

 Water hose in VHC Apparatus Bay

 Cabinet and counter in VHC Watch Room

 Track lighting in VHC Museum

 3-bay sink in EMS Training Storage Room

Lighting in VHC Individual Bunk Room

 Cabinets in VHC Laundry

 Front ramp on VHC east side

 Preparing for parking lot paving

 
Preparing for EMS Bay exterior lighting

 VHC Bay exterior lighting. West side.

Preparing for paving along Orange Street.

Friday, April 6, 2012

4/6/2012 Ship News Now Article

New emergency services building nears completion

6 April 2012
By MORGAN YOUNG
Staff writer
Officials from Vigilant Hose Company say it won’t be long before the doors to the new Shippensburg Area Emergency Services Building on Walnut Bottom Road will be open.
Construction on the 30,000-square-foot building, which will house a new station for Vigilant Hose and Shippensburg Area EMS, is scheduled to be complete next month, according to Kevin Nehf, Vigilant Hose Company vice president.
“Mainly it’s just details (of the building) that they’re doing now,” he said. “Most of the painting has been started if not done. I (visit) every week and every week it’s, like, ‘wow.’”
Nehf said the emergency departments are tentatively planning to open the new station on June 16. Members will close the old station on King Street the same day and march to the new $6.3 million facility.
Features of the new building include a training area, a study room for service volunteers attending school, and a services museum where the company’s recently restored 500-pound station bell will be housed.
Five bays for each agency are included in the facility, which due to space limitations has had to store its five ambulances and three emergency vehicles outdoors.
“For the Vigilant side I think they’re going to miss the fire house — there’s a lot of history there — but I think they’re excited about moving to the new station,” Randy O’Donnell, Shippensburg Fire Chief, said.
The facility also has several environmentally friendly features include a 10,000-gallon rainwater collection system to wash emergency vehicles; high-efficiency HVAC systems; LED lighting with occupancy sensors; and other local materials that will be installed in the building, helping to reduce costs.
“You can feel the guys starting to get excited about it,” Nehf said.
The fire company old station, which is about 100 years old, has been sold to next door neighbor Shippensburg First Church of God. Church officials said the building was purchased to expand the church’s ministry areas and classrooms.
“That right now is the general plan,” said Senior Pastor Paul Tatum. “It’s actually going to be a three- to four- month process of making the master plan. Once we kind of come up with the master plan we’ll probably more than likely redo the floor plan.”
——————
Morgan Young can be reached at myoung@shipnewsnow.com and 262-4753, or follow her on Twitter @ShipNewsGirl.

For original online article... http://www.shipnewsnow.com/2012/04/new-emergency-services-building-nears-completion/

Sunday, April 1, 2012

4/1/2012 Cabinets, Counters and Doors

 West Side.

 South Side.

East Side.

Cabinets in the VHC Copier Nook.

 VHC Chief's Office with door.

 VHC Deputy and Assistant Chief's Office.
With windows looking out over the Apparatus Bay.

 EMS TV Room.

 Study.

 Back Stairway from Fitness Room to Study.

 Epoxy floor drying in Ambulance Bay.

 EMS Office with door.

 Progress in the IT Room.

 In floor heat controls under steps in VHC Apparatus Bay.

 VHC Gear Wash Room with 3-bay sink for SCBA maintenance.

 Work benches in the VHC Engineer's Room.

 VHC Mezzanine in the Apparatus Bay. Looking to Hose Tower steps.

 Cabinetry for in the VHC Watch Room in VHC Apparatus Bay.

 Mailboxes in the VHC Watch Room.

 Work counters in the VHC Watch Room.

 White board on the back wall of the VHC Watch Room.

 Main 1st floor Lobby. Multipurpose Room on the left.

 VHC Men's Shower/ Locker Room.

 Emergency lights in the VHC Bunkroom corridor.

 VHC Kitchen cabinets.

Panorama of the 1st floor Mechanical room.