Friday, April 6, 2012

4/6/2012 Ship News Now Article

New emergency services building nears completion

6 April 2012
By MORGAN YOUNG
Staff writer
Officials from Vigilant Hose Company say it won’t be long before the doors to the new Shippensburg Area Emergency Services Building on Walnut Bottom Road will be open.
Construction on the 30,000-square-foot building, which will house a new station for Vigilant Hose and Shippensburg Area EMS, is scheduled to be complete next month, according to Kevin Nehf, Vigilant Hose Company vice president.
“Mainly it’s just details (of the building) that they’re doing now,” he said. “Most of the painting has been started if not done. I (visit) every week and every week it’s, like, ‘wow.’”
Nehf said the emergency departments are tentatively planning to open the new station on June 16. Members will close the old station on King Street the same day and march to the new $6.3 million facility.
Features of the new building include a training area, a study room for service volunteers attending school, and a services museum where the company’s recently restored 500-pound station bell will be housed.
Five bays for each agency are included in the facility, which due to space limitations has had to store its five ambulances and three emergency vehicles outdoors.
“For the Vigilant side I think they’re going to miss the fire house — there’s a lot of history there — but I think they’re excited about moving to the new station,” Randy O’Donnell, Shippensburg Fire Chief, said.
The facility also has several environmentally friendly features include a 10,000-gallon rainwater collection system to wash emergency vehicles; high-efficiency HVAC systems; LED lighting with occupancy sensors; and other local materials that will be installed in the building, helping to reduce costs.
“You can feel the guys starting to get excited about it,” Nehf said.
The fire company old station, which is about 100 years old, has been sold to next door neighbor Shippensburg First Church of God. Church officials said the building was purchased to expand the church’s ministry areas and classrooms.
“That right now is the general plan,” said Senior Pastor Paul Tatum. “It’s actually going to be a three- to four- month process of making the master plan. Once we kind of come up with the master plan we’ll probably more than likely redo the floor plan.”
——————
Morgan Young can be reached at myoung@shipnewsnow.com and 262-4753, or follow her on Twitter @ShipNewsGirl.

For original online article... http://www.shipnewsnow.com/2012/04/new-emergency-services-building-nears-completion/

Sunday, April 1, 2012

4/1/2012 Cabinets, Counters and Doors

 West Side.

 South Side.

East Side.

Cabinets in the VHC Copier Nook.

 VHC Chief's Office with door.

 VHC Deputy and Assistant Chief's Office.
With windows looking out over the Apparatus Bay.

 EMS TV Room.

 Study.

 Back Stairway from Fitness Room to Study.

 Epoxy floor drying in Ambulance Bay.

 EMS Office with door.

 Progress in the IT Room.

 In floor heat controls under steps in VHC Apparatus Bay.

 VHC Gear Wash Room with 3-bay sink for SCBA maintenance.

 Work benches in the VHC Engineer's Room.

 VHC Mezzanine in the Apparatus Bay. Looking to Hose Tower steps.

 Cabinetry for in the VHC Watch Room in VHC Apparatus Bay.

 Mailboxes in the VHC Watch Room.

 Work counters in the VHC Watch Room.

 White board on the back wall of the VHC Watch Room.

 Main 1st floor Lobby. Multipurpose Room on the left.

 VHC Men's Shower/ Locker Room.

 Emergency lights in the VHC Bunkroom corridor.

 VHC Kitchen cabinets.

Panorama of the 1st floor Mechanical room.

Sunday, March 25, 2012

3/25/2012 EMS Ramp, Vinyl Floors and Stucco

 West Side

 South Side

East Side

 EMS Ramps ready for concrete. Shows the 10 feet of heated ramp outside the doors (same as both the entrance and exit doors to VHC Apparatus bays) Taken Wednesday, 3/21/2012.

 EMS Bunk room hallway. Looking east towards VHC Offices.

 Fire extinguishers are mounted.

 EMS Living Area.

 EMS Gear Room. Ambulance bays are to the left.

 EMS Ambulance bays. Two doors on the left are the Gear Room.
Next is door to EMS Living Area, Decon Room and Storage Room.

 IT Room finally getting organized.

 Doorway to the Conference Room and the Elevator, 2nd floor.

 Flooring in Lobby and Multipurpose Room.

 Water Fountains in the Multipurpose room lobby.

 VHC corridor looking from the Watch Room to the hallway to the Kitchen.

 Epoxy floors are done in VHC Apparatus Bay.

 Epoxy floors and stripes are done in VHC Apparatus Bay.

 VHC Apparatus Bay. Stairs to 2nd floor VHC Offices.
In floor heating controls.

 VHC Gear Room.

 VHC restroom.

 VHC Kitchen.

 West side of VHC Bays. Bollard covers in place.

 The wall at the Generator is done.

 Front of EMS Bays. Bollard covers in place.

 EMS Ramp onto Orange Street.

 Orange Street side, last of the brick work is done.

East Side of VHC, the exit side. Stucco over doors is done.