Sunday, October 9, 2011

10/9/2011 More Walls, Concrete Planks and a Concrete Floor

In addition to these pictures I have added the Artist Renderings to the bottom of the page, including a view of the west side.

 Panorama of the west side (town side)

 Orange Street side. Concrete planks have been set over the Under Ambo Storage area. On top this will be three EMS bays, EMS Gear Room and the Study.

North side rooms. Open Storage, Storage, Gear Wash Room, Engineers Room and Hose Tower.

 Walnut Bottom Road East, Exit only. Note how close the pole is.

 Walnut Bottom Road West entrance/exit.

 Walnut Bottom Road west entrance/exit.

 Walnut Bottom road west entrance/exit. Some of the concrete drive is poured.

 West side of VHC Apparatus bays. The doors are starting to go up.

 Under Ambo Storage.

 South side of VHC Apparatus Bay. This is the wall to the Gear Room.

 MultiPurpose Room.

 VHC Gear Room. Through those doors is the Apparatus bay.

 VHC Living area and bunk area. Shower/Locker Rooms along back wall (left).

 Elevator shaft. Stairwell behind it (right).

 Mechanical Room.

 Far left is the hallway to Apparatus Bay, next is a restroom and right is the VHC Laundry room. Taken from hallway, Kitchen/TV Room is behind me.

 Another view of the VHC Gear Room looking towards the Apparatus Bay. Towards where I'm standing and across the hall from the Gear Room doors will be the doorways to the Bunk Rooms.

 Under Ambo Storage area. Fitness Room is to the left. There is a concrete plank ceiling and a concrete floor now.

 Under Ambo Storage area, this is the Electrical Room.

 Under Ambo Storage area, again. Fitness room is at the far end toward VHC living area.

 West side looking northeast. Shows VHC Apparatus doors.

 Outside west corner of Under Ambo Storage. Generator will sit right here.

 Walnut Bottom Road east exit only. Note pole on left side.

 Training hatch from Mezzanine to VHC north side Storage Room. When open this hatch can be used for rope rescue training.

Open Storage at north side of VHC Apparatus Bay. Concrete planks have been set on the Mezzanine. There will be a Storage Room built on this side of the Mezzanine.

Sunday, October 2, 2011

10/2/2011 More Blocks, More Plumbing, More Rain



This is the north side of the VHC Apparatus Bay. This week they set the steel above the open storage area. The rooms beside that, left to right, are Storage Room, Gear Wash Room, Engineer's Room and Hose Tower. There will be a mezzanine above all of these (except the Hose Tower) with a small storage room on the west (left) side of the Mezzanine. To the left side of the picture is the second bay door opening.

 North side rooms again.

 Looking out of the Hose Tower.

 Looking at the east side of the VHC Apparatus Bays. Only the first two bay doors are visible.

 Looking across the VHC Apparatus Bays to the VHC Living Areas.

 On the bottom left of this picture is the 'Back' door to the VHC. Looking straight ahead would  be a hallway, Restroom, Laundry and Gear Room.

 VHC Kitchen and TV Room. Across the long wall will be the Women's and Men's Showers/ Locker Rooms and Men's and Women's Restrooms for the MultiPurpose Rooms.

 Looking across the VHC Kitchen, other side of the wall is the Fitness room, beyond that is the Under Ambo Storage Area. Starting to see the door to the Pantry (right side short wall).

 Multipurpose Room. I'm standing near the VHC Watch Room.

Outside the Under Ambo Storage Area.

Saturday, October 1, 2011

8/12/2002 The University Lodge Burns

Shippensburg Sentinel article 8/14/2002



News-Chronicle article 8/16/2002



Remember, if you click these articles you can read them better.

Friday, September 30, 2011

9/30/2011 Building Renditions

Finally. Here is the archetects renderings of the building so you can better visualize the building process. The SA-EMS is facing Orange Street and the VHC is viewed as you approach it on Walnut Bottom Road driving towards town. I will get the floor plans up next week. I labeled these "Plans" so at any time just click on the plans label in the sidebar to bring this post up. Remember click these pictures and they get bigger.

The RED is standard brick (4" x 8"). The WHITE is split-face block (8" x 16"). There is two different shades of the white split-face, you can see this at the second floor line (but not so much in these renditions). There is also ground-face bricks (4" x 16" bricks that have been ground smooth) at ground level of the building below the window line on the Orange Street side and around the base of the hose tower and face of the building on the Walnut Bottom Road side.

Sunday, September 25, 2011

9/25/2011 It's Starting to Look Like Something

 Picture from the northwest looking east.

 From the west looking east through the VHC Apparatus Bays.

 Looking south at the Under Ambo Storage area.

 Looking southeast across VHC living area. Vertical support footers have been poured.

Looking north into VHC Storage, Gear Wash room, Engineers room and Hose Tower. There will be a mezzanine over these rooms.

 Trench drain at VHC entrance off Walnut Bottom Road.

 Northeast corner of VHC Apparatus Bay.

 Looking northeast into north end of VHC Apparatus Bay.

 Bollards are set on west side of VHC Apparatus Bays.

 Under Ambo Storage and Electrical Room.

 Looking north along west face of VHC Apparatus Bay. Bollards on either side of bay doors.

 VHC Gear Wash Room, door frame and grease separator in place.

 Looking northwest across VHC Apparatus Bay.

 Exterior of Multipurpose Room. Doorway and window set.

 Orange Street side, southeast corner, not much new out here yet.

 Orange Street side, southwest corner, not much new here either.

Northwest corner of  Under Ambo Storage, shows man door and garage door. Block footer in front is for retaining wall to block generator.

 Southeast corner, inside. Multipurpose Room on the left, Stairwell on the right and Elevator pit in the center.

Inside north face of Under Ambo Storage area, fitness room to the left.

To answer some questions, both asked and unasked, all pictures can be enlarged by simply double clicking them. Panoramas will show some distortion on the edges (don't think the walls are crooked). I know it seems that most pictures show VHC areas, and they do, all of EMS is upstairs and once work begins up there you will see pictures of those areas. And finally, yes, I am taking more pictures than you see here (usually between 60 and 100 every week). I am trying to get pictures of how things are built, how pipes are laid underground and multiple views of most rooms and the building itself. And finally (again finally) feel free to leave comments or questions in the comment section (just sign it with a name) and I will respond or get a response.