Sunday, February 19, 2012

2/19/2012 Arches, Study and Ceiling Grid

 West Side.

 South Side.

East Side.

 Arches in progress over VHC Apparatus Doors.

 Porch roof to the rear of the VHC Living area.

 Electrical Room in Under Ambo Storage area.

 Overhead door in Under Ambo Storage area.

 VHC Vehicle exhaust parts and pieces.

 VHC Individual Bunk Rooms. Ceiling grid has started.

 VHC Bay door openers in the Watch Room.

 Looking up into the Hose Tower at the catwalk for hanging hose on the pipe hangers.

 First floor lobby. Multipurpose Room left, VHC Museum and EMS Storage room right.

 IT Room. All the computers, radios, telephones and door controls are located here.

 One of the large EMS Bunk Rooms. These are set up to fit 5 bunks.

 Building the EMS Gear Room, Storage Room and the Study 
in the back of the Ambulance Bay.

 Inside of center Ambulance bay door. 
Walls are painted, doors are coming soon.

 Generator and cooling tower.

Arches over the center Ambulance Bay door.

No comments: