12/11/2011 Interior Block Walls and More Roof

West Side

South Side

East Side

The pads for the Generator and Cooling Tower have been poured.

Stairway from 1st floor Fitness Room to 2nd floor Study.

Storage Room above the Mezzanine and Training Wall got done this week.

Hallway from VHC living area to VHC Apparatus bay.

VHC Gear Room looking east.

Stairs are set in the southeast stairway (by the elevator).

EMS Storage room off the Ambulance Bay. To the left is the Decon Room and Laundry.

Looking across 2nd floor to the east.

Looking across EMS TV Room and Kitchen.

Elevator and Elevator Mechanical Room on the 2nd floor. Southeast stairway and 2nd floor entrance on the right.

EMS Storage room and Decon Room off the Ambulance Bay. The door is to the Laundry from the EMS living area.

Southeast stairway from the 2nd floor.

Hose Tower at the northeast corner of VHC Apparatus Bay.

Once the roof is on and the 2nd floor is in the dry, drywall will be hung on the bottom of the roof trusses and the 2nd floor interior walls can be started.